01 — Build tracker

The Hartwell

Jefferson Township · Franklin County · Columbus, Ohio

Plan — The Hartwellpartial landModern Farmhouse
58%complete

6 of 11 milestones done · Mechanicals rough-in underway

Timeline assumes partial land — access was cleared and the remaining scope was known before contract, so site work ran two weeks instead of the months raw land needs. Finished lots skip most of that phase; raw land adds site work and sequential permitting before foundation.

Contract price
$636,145+1.2% site variance — absorbed by contingency

Locked at contract — Feb 16, 2026. Moves only by signed change order. The relocated septic field ran $7,600 over the site-work allowance — 1.2% of contract, covered by contingency. Everything else is tracking to the locked price.

Contract signed
Feb 16, 2026

One team carries the project from land closing through construction. The build contract above excludes the land purchase (closed separately) and includes the approved change order below.

Estimated certificate of occupancy
Oct 5 – Oct 23

A window, not a promise date — currently tracking ahead of the 912 month range we quote for partial land.

02 — Timeline

Eleven milestones, planned against actual

Planned dates were set at contract on partial land. Actual dates are what happened — including the six days the signed window upgrade added to framing. Where they differ, you see both.

  1. 01

    Contract & deposit

    Complete
    Planned
    Feb 16 – Feb 20
    Actual
    Feb 16 – Feb 18

    Price locked at the configurator estimate after the site review found nothing to add. Deposit received and the construction loan closed — no draw funds until an inspector passes the work it pays for.

  2. 02

    Permits & approvals

    Complete
    Planned
    Feb 19 – Mar 27
    Actual
    Feb 19 – Mar 25

    Franklin County returned the full permit set in five weeks — inside the 3–8 week range we plan for in the Columbus metro. The septic permit cleared the county health district in the same window, no re-review.

  3. 03

    Site work

    Complete
    Planned
    Mar 23 – Apr 10
    Actual
    Mar 26 – Apr 9

    Drive cut from the road frontage, pad benched, the electric extension trenched, erosion control in. The septic field's first perc location failed and the field moved east: $7,600 over the site-work allowance — the 1.2% variance shown at the top of this page, covered by contingency, not a change order.

  4. 04

    Foundation

    CompleteDraw 1 — funded
    Planned
    Apr 8 – Apr 24
    Actual
    Apr 10 – Apr 16

    Footings, walls, and slab poured across five working days of dry weather. The as-built survey pins came back within a half inch of plan. County passed both concrete inspections; draw 1 funded the next day.

  5. 05

    Framing

    CompleteDraw 2 — funded
    Planned
    Apr 20 – May 28
    Actual
    Apr 20 – Jun 3

    Six weeks of clean framing. The approved window upgrade added six days to this phase — you see it in the actual dates, not buried in a revised plan. Framing inspection passed Jun 4; draw 2 funded Jun 5.

  6. 06

    Roof & dry-in

    Complete
    Planned
    Jun 1 – Jun 16
    Actual
    Jun 4 – Jun 18

    Standing-seam roof on and the upgraded window package set. The house is dry — weather can slow interior trades now, but it can no longer stop them.

  7. 07

    Mechanicals rough-in

    In progressDraw 3 — releases at inspection
    Planned
    Jun 19 – Jul 24
    Actual
    Jun 19 – ongoing

    Plumbing and electrical rough are complete; HVAC finishes this week after a four-day crew delay we absorbed by resequencing. The county rough-in inspection is booked for Jul 24 — draw 3 releases on a pass.

    Live — weekly updates from this phase
    Weekly updates for the current milestone
    1. Jun 26, 2026

      Plumbing top-out underway

      Supply and drain runs are in the first-floor walls. HVAC mobilizes Monday, electrical the week after.

    2. Jul 3, 2026Delay — absorbed

      HVAC started four days late

      Straight talk: our HVAC contractor arrived Thursday instead of Monday — a prior job ran over. We resequenced electrical rough ahead of ductwork to keep the site full, so the slip is absorbed inside this phase and your completion window is unchanged.

    3. Jul 10, 2026

      Ductwork and wire

      Trunk lines and both air handlers are set; electrical rough is about 60% with the panel landed. The scullery circuit layout Priya adjusted in design saved a re-pull here.

    4. Jul 17, 2026

      Ready for inspection

      Electrical rough is done and low-voltage is pulled. We ran our own pre-inspection walk this morning — three boxes to strap, one vent to re-slope, both fixed before the county sees them. The mechanical rough-in inspection is booked for Friday, Jul 24; draw 3 releases when it passes.

  8. 08

    Insulation & drywall

    UpcomingDraw 4 — releases at inspection
    Planned
    Jul 27 – Aug 21

    Insulation goes in only after a passed rough-in inspection, then hanging and finishing. Three weeks where the house turns from a frame into rooms. Draw 4 releases on the drywall inspection.

  9. 09

    Interior finishes

    Upcoming
    Planned
    Aug 24 – Oct 2

    Cabinets, the oak stair, tile, paint, trim, and fixtures — the longest phase by feel. Priya's selection sheet from your configurator session is the single source of truth on site.

  10. 10

    Punch list & CO

    UpcomingDraw 5 — final at CO
    Planned
    Oct 5 – Oct 23

    Our own punch walk, then yours, then the county's certificate of occupancy. Keys change hands at CO — we don't call it done before the county does.

  11. 11

    Warranty period

    Upcoming
    Planned
    Oct 23, 2026 – Oct 23, 2027

    Twelve months of scheduled checkups — a 60-day and an 11-month walkthrough — under a written workmanship warranty, with 10-year structural coverage. Same team, same phone numbers.

03 — The open ledger

Money, inspections, and paperwork in the open

The parts of a build that usually live in a contractor’s filing cabinet. Draw amounts are fixed percentages of the contract price, every draw is gated by a county inspection, and the one change order is here with both signatures on it.

Construction loan

Draw 2 of 5 funded
$222,651 released of $636,145. Each draw is a fixed percentage of contract price and releases only on an inspected milestone — never on a calendar date.
  1. 01Foundation

    Funded Apr 17, 2026

    $95,422

    15%

  2. 02Framing

    Funded Jun 5, 2026

    $127,229

    20%

  3. 03Mechanicals

    Releases on the passed mechanical rough-in inspection (Jul 24).

    $159,036

    25%

  4. 04Drywall

    Releases on the passed drywall inspection.

    $159,036

    25%

  5. 05Final

    Releases at CO, after your walkthrough.

    $95,422

    15%

Inspections

County-verified checkpoints
Third-party inspections gate every draw. We schedule them; the county calls the pass.

Last passed

Framing inspection

Passed Jun 4, 2026 · Franklin County Building Department

Next up

Mechanical rough-in inspection

Scheduled Jul 24, 2026 · Franklin County Building Department

Plumbing, electrical, and HVAC rough are inspected together. A pass releases draw 3.

Change orders — 1 of 1 approved

CO-01 · Window package upgrade
Standard package → expanded glazing: enlarged rear openings with a transom line across the great room.
Contract
+$17,945
Schedule
+6 days
Approved

Signed by both parties May 30, 2026

No other changes. The locked price moves only like this — scoped, priced, and signed by both parties before any work shifts.

Your team

Three people, contract to warranty
The people who write your weekly update are the people on your site — no handoffs, no call center.
  • Maren

    Project lead

    Your single point of contact — owns budget, schedule, and the weekly update.

  • Dale

    Site superintendent

    On site daily; runs trades, inspections, and quality walks.

  • Priya

    Designer

    Carried your configurator selections into the field paperwork, sheet by sheet.

04 — Weekly updates

Every Friday, in plain language

Eight updates so far, newest first — including the one where the HVAC crew showed up four days late and what we did about it. We publish the misses too; a tracker that only shares good news is marketing.

  1. Jul 17, 2026

    Mechanicals rough-in

    Ready for inspection

    Electrical rough is done and low-voltage is pulled. We ran our own pre-inspection walk this morning — three boxes to strap, one vent to re-slope, both fixed before the county sees them. The mechanical rough-in inspection is booked for Friday, Jul 24; draw 3 releases when it passes.

  2. Jul 10, 2026

    Mechanicals rough-in

    Ductwork and wire

    Trunk lines and both air handlers are set; electrical rough is about 60% with the panel landed. The scullery circuit layout Priya adjusted in design saved a re-pull here.

  3. Jul 3, 2026

    Mechanicals rough-in

    Delay — absorbed

    HVAC started four days late

    Straight talk: our HVAC contractor arrived Thursday instead of Monday — a prior job ran over. We resequenced electrical rough ahead of ductwork to keep the site full, so the slip is absorbed inside this phase and your completion window is unchanged.

  4. Jun 26, 2026

    Mechanicals rough-in

    Plumbing top-out underway

    Supply and drain runs are in the first-floor walls. HVAC mobilizes Monday, electrical the week after.

  5. Jun 19, 2026

    Roof & dry-in

    Dried in

    Windows and exterior doors are set and the house is officially dry. The plumbing crew staged material today; top-out starts Monday. From here, weather can slow us but it can't stop us.

  6. Jun 12, 2026

    Roof & dry-in

    Roof panels going on

    Standing-seam panels went on over a dry underlayment week, and the upgraded window package is being set floor by floor.

  7. Jun 5, 2026

    Framing

    Framing inspected, draw 2 funded

    Franklin County passed the framing inspection Thursday; draw 2 funded today. Your upgraded window package (change order 01) delivered to site — its six added days are already reflected in the milestone dates.

  8. May 29, 2026

    Framing

    Framing wraps next week, engineer walk done

    Second-floor plates and the stair opening went in this week; final bracing runs Monday through Wednesday. Maren and Dale walked the frame with the structural engineer this morning — two truss hangers flagged and corrected the same day.

05 — Site record

The site, week by week

On a real build these are photographs from Dale’s Friday walk, archived to your project record. This sample draws them instead — we don’t stage fake photos.

Foundation formsApr 14, 2026
Framing, second floorMay 14, 2026
Trusses setMay 28, 2026
Mechanical rough-inJul 8, 2026
Drywall stagedJul 17, 2026
Front elevation, dried inJul 19, 2026